This project concerns the replacement of an existing gas heating system by a hybrid HP+gas solution in an existing multifamily building. With the goal of having the maximum annual heat production from HP origin, six air/water heat pumps were implemented on the rooftop. One of the previous gas boilers was kept for the peak loads in winter.

The existing MFH (multi-family building), built in 1992 in Geneva, contains 68 apartments, within 4 floors, plus commercial establishments on the ground floor (restaurant, bakery, …). It suffered no major envelope retrofit before this project and the total gas consumption amounted to 1’000 MWh/yr (for space heating and domestic hot water of 7’563m²). (Photo credit SIG, CSD Ingénieurs SA)

Lessons learned

Ongoing monitoring, but so far:

  • Major air HP constraints encountered: noise emissions, vibrations, safety… These implied important costs and planning work.
  • Hybrid HP+gas system: optimization of the gas boiler switching point is crutial for a good HP share in the overall heat production (specially with an old boiler without variable power output).
  • The constraints of the old heat and DHW distribution system should not be underestimated.

Key facts

Building Heat pump and source
LocationGeneva, Switzerland
Number of HP6
Construction1992Installed power6 x 30 kW
Heat distributionradiatorsOperation modehybrid (HP + gas)
Heated area7,563 m²Heat sourceambient air
Level of insulationlow (1992 standard)Existing gas boiler240 kW
Heating systemDomestic hot water
Heat demand700 MWh/yrType of systemcentral
Heating temperature65 °C (@ -7° ext)
Max. temperature60 °C
Circulation systemyes
Other information
Electric and gas energy consumption190 MWh/yr electric

230 MWh/yr gas

Investments costsunknown
PV installationno

 

Description of the technical concept

This project, part of a Geneva pilot program to replace fossil fuel boilers by heat pumps (HP) in MFH, concerns the replacement of a gas heating system by a hybrid HP+gas heating system. With the goal of having a maximum heat production from HP origin, six 30 kW air/water heat pumps were implemented on the rooftop. For the peak loads in winter, a 240 kW gas boiler was maintained.

It should be mentioned that:

  • The building rooftop was retrofitted before the HPs were installed. No other retrofit action was undertaken.
  • The heat and DHW distribution system was not modified.

The 6 HPs are divided into 2 groups of 3. 1 group exclusively for space heating, the other can either do space heating or domestic hot water. The gas boiler, when functioning, can work simultanioulsy with the HPs.