Tokyo Electric Power Company R&D Center was completed in September 1994. This building was supposed 30% (approx.) energy savings attained by the adoption of the cold air distribution system and various other techniques and technologies for energy conservation and operation management. Tokyo Electric Power Company R&D Center has undertaken a wide range of building commissioning including building management since the completion of the construction. Now that fifteen years have passed since the completion, the R&D Center has enhanced the energy-saving performance well beyond the levels previously measured values.